Strategic Location & Size
 Located 80 km from Ahmedabad (Approx. 2-hour drive)
Located 80 km from Ahmedabad (Approx. 2-hour drive) Just 20 km from DSIR, boosting industrial connectivity
Just 20 km from DSIR, boosting industrial connectivity Spanning 1,426 hectares, with 75 hectares allocated for commercial development
Spanning 1,426 hectares, with 75 hectares allocated for commercial development
Why is Dholera Airport Important ?
 Boosts Connectivity : Eases congestion at Sardar Vallabhbhai Patel International Airport (Ahmedabad)
Boosts Connectivity : Eases congestion at Sardar Vallabhbhai Patel International Airport (Ahmedabad) Supports DSIR & DMIC : Facilitates logistics for industries in Delhi-Mumbai Industrial Corridor (DMIC)
Supports DSIR & DMIC : Facilitates logistics for industries in Delhi-Mumbai Industrial Corridor (DMIC) Global Trade & Investment Hub : Enables faster import/export and industrial expansion
Global Trade & Investment Hub : Enables faster import/export and industrial expansion
Upcoming International Air Cargo Operations
Dholera International Airport Company Limited (DIACL) intends to commence international air cargo operations in the initial phase from June/July 2025. This will provide a major boost to global trade and make Dholera a logistics powerhouse.
Enhanced Connectivity
A Greenfield Expressway is under construction to provide seamless road connectivity between Dholera Airport and Ahmedabad. The project is in its advanced stage and will reduce travel time significantly.
Development Timeline & Key Milestones
 2010: Airports Authority of India (AAI) conducted feasibility study and granted technical clearance
2010: Airports Authority of India (AAI) conducted feasibility study and granted technical clearance 2012: Gujarat Government set up Dholera International Airport Company Ltd. (DIACL)
2012: Gujarat Government set up Dholera International Airport Company Ltd. (DIACL) 2014: Central Government provided site clearance
2014: Central Government provided site clearance 2015: Environmental approval granted
2015: Environmental approval granted 2018: AAI acquired 51% stake in DIACL, Gujarat Government retained 33%, DMICDC held 16%
2018: AAI acquired 51% stake in DIACL, Gujarat Government retained 33%, DMICDC held 16% 2019: AAI & Gujarat Government signed MoU for airport construction
2019: AAI & Gujarat Government signed MoU for airport construction 2021: ₹987 crore Phase 1 tender released; Varaha Infrastructure awarded civil works contract
2021: ₹987 crore Phase 1 tender released; Varaha Infrastructure awarded civil works contract 2022: Union Cabinet sanctioned ₹1,305 crore for Phase 1 development
2022: Union Cabinet sanctioned ₹1,305 crore for Phase 1 development 2024: Yashnand Engineers & Contractors awarded ₹333 crore contract for passenger terminal, ATC tower & cargo complex
2024: Yashnand Engineers & Contractors awarded ₹333 crore contract for passenger terminal, ATC tower & cargo complex
Key Features of Phase 1 (Completion by December 2025)
 Runway: 3,200 meters (4E category aircraft compatible)
Runway: 3,200 meters (4E category aircraft compatible) Passenger Terminal: Modern facilities for seamless travel
Passenger Terminal: Modern facilities for seamless travel International Cargo Hub:  Operational from June/July 2025
International Cargo Hub:  Operational from June/July 2025 ATC Tower & Aprons: Advanced air traffic management system
ATC Tower & Aprons: Advanced air traffic management system
Dholera International Airport is not just an airport—it’s a catalyst for economic transformation, attracting global businesses and investors. With world-class infrastructure and strategic connectivity, it’s set to redefine India’s aviation landscape!












 Dholera airport can become aerospace industry's focal point of development: Sinha
Dholera airport can become aerospace industry's focal point of development: Sinha The greenfield airport at Dholera should finish by 2020
 The greenfield airport at Dholera should finish by 2020 
 Experts to bid for Dholera airport DPR
 Experts to bid for Dholera airport DPR
 Civil Aviation Ministry Gives Clearance For 4 Greenfield Airports
Civil Aviation Ministry Gives Clearance For 4 Greenfield Airports
 
 